The rehabilitation project for Baia Mare Water Treatment Plant has reconsidered the entire initial treatment process, introducing modern procedures and integrating a substantial part of the existing ones in order to obtain a treatment system duly adapted to the raw water quality and to the treated water requirements in accordance with Law 458/2002 and EC Directive 98/83/EC.

The main rehabilitation works of the plant refer to:

  • Introducing a new settlement step in the technological process;
  • Facilities for sludge treatment;
  • Introducing a control, automation and data system.

Design Data

Drinking water treatment capacity : 9,50l/s (82,000 m3/day)

Compliance with drinking water quality standards : Law 458/2002 (regarding the turbidity parameter only ≤1 NTU) and EC Directive 98/83/EC

Raw water turbidity : 1-80 NTU

Minimum residual Chloride contents : 1 mg/l

Sludge treatment capacity : 30 m3/zi

Dry substance content of treated sludge : 20%

Wastewater resulting from water treatment process according to: NTPA 001/2002 updated 2005

Rehabilitation works

Due to the rehabilitation process, the Treatment Plant is improved as to:

  • Replacement of reagent treatment and dosing installations ;
  • New fine filters for de-gritting;
  • New primary treatment by lamellar settling MULTIFLOTM type with TURBOMIXTM for physical-chemical settling;
  • Rehabilitation of existing descending (rapid) sand filters ;
  • Decommissioning of existing ascending (contact) sand filters and conversion into descending sand filters;
  • Replacement of Chlorine storage / dosage facilities ;
  • Auxiliary installations for washing water from rehabilitated filters ;
  • New sludge treatment for technological process sludge including :

oSludge storage tank ;

oSludge thickening installation;

oSludge dewatering installation ;

  • Monitoring and control (SCADA), general works ;
  • Replacement of treated water pumps that provide water to Ferneziu District.